The intersection of N.M. 4 & East Jemez Road prior to work completed in the 2022 construction season. Courtesy/LAC
COUNTY News:
Crews resumed construction this week on a project to improve the intersection of N.M. 4 and East Jemez Road.
During Phase 1-B, expected to last through late May 2023, crews are working on both sides of N.M. 4 as well as on the north shoulder of East Jemez Road.
Traffic impacts in place:
- Access to the parking area for the Bandelier National Monument Tsankawi Unit will be COMPLETELY CLOSED as of Monday, April 3, 2023. No alternate access will be provided while the National Park Service builds a new parking area and access road to align with the improvements being made as part of this project. The new access is expected to be open in late October 2023;
- Crews are removing the median islands and placing detour pavement at the intersection of N.M. 4 and East Jemez Road;
- The existing traffic signal will be removed and a temporary signal will be installed; and
- The speed limit throughout the construction area is reduced to 35 MILES PER HOUR.
During construction, all existing travel lanes on N.M. 4 and East Jemez Road will remain open during peak travel times – 6:30-8:30 a.m. and 4-6 p.m. Monday through Friday. Any lane closures will occur during non-peak hours and flaggers will direct traffic. All construction is weather permitting and is subject to change without notice.
Motorists are encouraged to slow down and give themselves additional time to reach their destination.
More construction phases will follow, with the project expected to be completed in late 2023.
About NMDOT Project CN 5100480:
The project is being funded by the U.S Department of Energy’s (DOE) National Nuclear Security Administration (NNSA) as part of a settlement agreement with the State of New Mexico and is being constructed in cooperation with the New Mexico Department of Transportation. The intent of the project is to reduce commute times for workers of Los Alamos National Laboratory, particularly those returning home in the evening hours, as well as improve safety and drainage in the area. The project includes new roadway construction of N.M. 4 and East Jemez Road, improvements to storm drainage, new curb and gutter, new retaining walls, ADA ramps, intersection warning flashers, a new traffic signal, new lighting and roadway signing and striping.
For more information, contact Patti Watson at 505.245.3134 (direct office); 505.269.9691 cell; 1.800.687.3417 (toll-free) or eamil pattiw@cwastrategic.com.
Courtesy/LAC