COUNTY News:
Los Alamos County Public Works Department, in partnership with Department of Public Utilities and under contract with TLC Plumbing & Utility, will begin work on the Bathtub Row Reconstruction Project.
The project will take place on Bathtub Row from Central Avenue to Peach Street, Peach/Nectar Street to 15th Street and utility improvements along 15th Street.
The project is divided into two phases with Phase 1 to be completed prior to winter. Phase 2 will start after a winter suspension, with a project substantial completion date of August 2025. (See Map Above)
The contractor will begin Phase 1 on Aug. 26, 2024, performing preliminary work, such as mobilization, construction staking, potholing and staging area setup with a full road closure on Bathtub Row from Central Ave. to Oppenheimer Drive (Mesa Public Library driveway).
Construction is scheduled to begin later that week or the following week. The project was presented at a public meeting conducted during the regularly scheduled Transportation Board meeting in March 2023.
Hours of Construction:
TLC Plumbing & Utility will work from 7 a.m. to 5 p.m., Monday through Thursday, with the addition of Fridays and weekends, as needed. Residents can expect large equipment, and construction noise.
Traffic Impact:
To minimize disruption, the contractor will notify and coordinate with affected business owners and residents for certain construction logistics, utility upgrades, and traffic changes as work progresses. Services such as mail delivery, trash and recycling collection, school bus, transit, and emergency services will be maintained.
Traffic should follow all detour signs. The detours will ensure ingress and egress to businesses and residences. Motorists and pedestrians are advised to use caution around construction activities and avoid entering the work zone.
Stay informed:
All questions, concerns, or special access needs should be sent to the Public Works Department at lacpw@lacnm.us or call 505.662.8150. We thank residents and business owners in advance for their cooperation and patience.
For project details, visit the County project webpage at https://lacnm.com/PW-Projects.
Interested individuals can also subscribe to the County Cone Zone e-Newsletter for project updates between the months of April and November – https://lacnm.com/Subscribe.